Project Cost Estimate
Status
Water Tower

$4.8M

Preparation of the construction site was started early September 2016.  A temporary easement on the east side of the site was acquired to eliminate traffic and avoid conflicts with the Fire Department along Tower Place Road during construction.
As of January, 2017, approximately 70'-80' of the concrete column has been poured and the construction remains on schedule to complete this fall.

Roadway Reconstruction - Type B Roads
$3M

Town East, Jobson and Tripp Roads were completed in December, 2016.  The Town is currently working with Dallas County to draft a Project Specific Agreement (PSA) to complete reconstruction of Barnes Bridge, Long Creek and Lawson Road.  The anticipated start date is May, 2017 and should take 3-4 months to complete.

Collins Road - US80 through Tripp Intersection
$8.6M
 

Council is being presented an updated estimate of right of way acquisition and construction cost in late January, 2017.  Council will then discuss and consider project financing and the tax implications to Sunnyvale residents of issuing a Certificate of Obligation up to $4,400,000.

.
Sunnyvale Center Industrial Park Water Lines

 Complete as of October, 2016
 State Highway 190