Town Projects
Current Town Projects
To view more information, click on the project name.
Project Cost Estimate
Status as of March 27, 2018
Water Tower

$4.8M

Construction site preparations were started in September 2016, and the new tower has been operational since November, 2017.

The contractor is finishing up punch-list items and the old tower should be demolished in late April.

Master Drainage Study
$250,000

To date the following has been completed:
• Phase 4 survey is complete
• Long Creek watersheds have been delineated, modeling is started
• Inlet level delineations for local area analysis are complete
• Phase 1 survey is in progress

Collins Road - US80 through Tripp Intersection
$8.6M

Engineering and design for the project were completed in early 2017. The Town is currently in the in the process of securing the necessary right of way and easements as well as coordinating with utility companies for the relocation of utilities (electric, cable, fiber, etc.) Both are anticipated to be complete later in the fall, with construction starting soon after.
Dallas County agreed to extend their 50/50 MCIP commitment an additional one million dollars to cover the increased costs to modify the project limits to include the consolidation of the two Tripp intersections. The modification enhances the overall safety, effectiveness and efficiency of the project for both the Town and the County.
In April 2017, Council approved issuing a Certificate of Obligation for $4,390,000.

.
Road Repair - Jobson and Barnes Bridge

 Construction on Barnes Bridge Road is expected to begin Monday, April 2nd, weather permitting and last approximately two weeks.

Repairs to Jobson Road between US Hwy 80 and Tripp Road will begin shortly thereafter.
 State Highway 190